Correctional Facility Pre-Installation Checklist

January 2, 2026

Summary

For Commercial Kitchen Equipment Installation Inside Secure Environments

Provided by Aldevra – Correctional Foodservice Systems

This checklist ensures the facility, custody staff, and installation team are fully prepared for a secure, compliant, and uninterrupted installation.

SECTION 1 — Facility Security & Clearance Requirements

1.1 Contractor Clearances

☐ All installers submitted for background checks

☐ Facility has approved all contractor personnel

☐ Temporary badges or security IDs prepared

☐ Contractor names entered into visitor/contractor logbook

☐ Escort officer(s) assigned for entire installation window

1.2 Restricted Access & Movement

☐ Approved access route provided (gate → sally port → work zone)

☐ Facility map or escort-only zones reviewed with contractor

☐ Installation times scheduled around inmate movement periods

☐ Tool/equipment staging area assigned and secured

SECTION 2 — Tool Control & Contraband Prevention

2.1 Tool Logging

☐ Facility-approved tool list submitted

☐ Serial numbers documented

☐ Entry inventory set for tool check-in

☐ Exit inventory process reviewed with escort officer

2.2 Prohibited Items Reviewed

☐ No personal bags, phones, or unapproved items

☐ No loose hardware or unsecured small parts

☐ All packaging materials accounted for during and after work

SECTION 3 — Delivery & Logistics Coordination

3.1 Delivery Clearance

☐ Delivery vehicle approved by facility

☐ Driver and crew listed on arrival manifest

☐ Sally port scheduling confirmed

☐ Security screening procedures provided to contractor

3.2 Path of Travel

☐ Doors, hallways, and sally ports measured for equipment clearance

☐ Escort staff aware of oversized items

☐ All obstacles removed (furniture, carts, storage racks)

☐ Temporary floor protection installed if required

SECTION 4 — Utility Readiness (Must Be Completed Before Install)

4.1 Electrical

☐ Correct voltage, amperage, and outlets installed

☐ Breakers labeled and accessible

☐ GFCI or disconnect switches installed per code

☐ Electrical contractor available onsite (if required)

4.2 Plumbing

☐ Hot/cold water lines terminated at correct locations

☐ Floor drains clear and properly trapped

☐ Backflow preventers installed where needed

☐ Final connections confirmed per manufacturer drawings

4.3 Gas (If Applicable)

☐ Gas shutoff valves tested and labeled

☐ Quick-connect couplings approved for institutional use

☐ Ventilation interlock compliance confirmed

4.4 Ventilation

☐ Hoods cleaned and inspected (UL 300 if cookline)

☐ Make-up air running properly

☐ Dampers functioning

☐ Negative/positive airflow verified

4.5 Refrigeration Lines (If Remote)

☐ Line sets installed

☐ Condensing unit pad prepared

☐ Penetrations sealed per security requirements

SECTION 5 — Work Zone Preparation

5.1 Area Access

☐ Work zone cleared of inmates

☐ Officer supervision assigned

☐ Perimeter secured during install

5.2 Space Clearance

☐ Old equipment removed

☐ Floors cleaned, walls repaired

☐ Storage rooms prepared for parts and packaging

5.3 Safety Requirements

☐ Lockout/tagout procedures reviewed

☐ Fire suppression disabled/enabled per code

☐ PPE requirements communicated to contractor

SECTION 6 — Packaging, Debris, and Material Control

6.1 Material Tracking

☐ All packaging accounted for upon entry

☐ No loose banding, nails, staples, or foam left unattended

☐ Debris removed immediately after installation

6.2 Final Sweep

☐ Officer and contractor conduct joint sweep of area

☐ Tool list reconciled

☐ All materials logged out of the facility

SECTION 7 — Testing, Training & Acceptance

7.1 Operational Testing

☐ Equipment powered on and tested

☐ All controls, gauges, valves, and safety mechanisms checked

☐ Tamper-resistant features verified

7.2 Staff Training

☐ Kitchen staff instructed on operation

☐ Chemical/detergent vendors notified for setup

☐ Inmate labor roles reviewed (if applicable)

7.3 Documentation

☐ Warranty registration completed

☐ O&M manuals delivered

☐ Preventive maintenance schedule provided

7.4 Final Sign-Off

☐ Deficiencies corrected

☐ Facility representative signs acceptance form